http://epaper.brecorder.com/2014/03/21/18-page/553389-news.html
“Wind
energy has massive potential “, CEO Sachal Energy Development
Kashif Mateen Ansari
is the CEO of Sachal Energy Development - a wind power IPP in Pakistan. Before
joining Sachal, a wholly-owned project of Arif Habib Group, Kashif has had more
than 20 years of diversified experience of leadership and management. His last
recent assignment was as the Chief Operating Officer of Askari Group overseeing
more than 30 companies.
A Harvard alumnus,
Kashif has served as a member of the executive board of Harvard Club of
Pakistan in 2012. He is also a Fellow of the Institute of Cost and Management
Accountants of Pakistan. Below is the edited transcript of a recent discussion with Kashif at his office in Islamabad, where he sheds light on the company he runs, the renewable energy industry as a whole and the prospects of, what he calls, the democratisation of energy in Pakistan.
“We have achieved all the major milestones. Earlier this month we signed the Energy Purchase Agreement with the NTDC, which is one of the most important milestones. Contracts including equipments and construction have also been finalised. Now we are waiting for the signing of implementation agreement, which will hopefully be done this month,” says Kashif.
For the uninitiated, the implementation agreement is an agreement between the project and the federal government. Not only does it set out the terms of the implementation of the project but also spells out the guarantees that come from the federal government.
Once the implementation agreement is signed, Sachal’s financial close can be expected within the ongoing financial year and Kashif says that due diligence is already under way with banking institutions. “The project will commence operations within 18 months after the financial close, which means we should be online by December 2015,” he said.
BANKING ON CHINA
“In the private sector we would be the first project in
Pakistan bringing Chinese financing into the country. The company has a debt to
equity of 80:20, and about 90 percent of the debt component is from China,” he
said.
The project’s EPC
contractor is also a Chinese firm called HydroChina, which is one of the
largest companies in the power sector in China. “Our wind turbine generator is
provided by a firm called Goldwind, which stood third globally last year and
the year before. Prior to that, it was first globally and the only reason it
has gone down because GE’s sales have gone up due to American spending on
wind,” says Kashif. Explaining the technology, Kashif said that Sachal’s is permanent magnet and direct drive. “Permanent magnet means that once the machine is stopped and the wind starts blowing again, this machine will not require any external excitation from the grid to start producing energy, which is a big thing.”
He says that most machines coming into Pakistan at the moment require an external excitation, if and when the machine is stopped and the wind starts blowing again. This means that if there is a problem with the grid, then you won’t be able to start producing from the wind. “We are among the the first few Pakistani projects to have this technology,” he said.
And how does direct
drive machine help? Kashif replies by explaining that his machine has no gear
box, which means it reduces the probability of breakdowns because the moveable
parts are reduced. “In turn it reduces the burden on the maintenance side and
it gives more reliability,” he said.
Following the
completion of its ongoing project, the firm plans to explore more projects in
wind. “Before exploring solar, we are looking to put up 200 megawatt wind
energy projects in total, spread over a time line of 7-8 years,” said Kashif.
WIND ENERGY PROSPECTS
IN PAKISTAN
Citing a study
conducted by the National Renewable Energy Laboratory, America, Kashif says
that the theoretical potential of producing wind energy is Pakistan is 133,000
MW that includes the two main corridors Nuk Kundi corridor in South Western tip
of Balochistan and the Gharo-Jhimpir corridor in Sindh. He adds that the
generation capacity factor in Pakistan is also decent at 33-34 percent,
compared to 40 percent in the best of wind corridors in the world. All this is hunky dory. But how much of this potential is realistic, considering the difficulties surrounding the Nuk Kundi corridor and the usual differences between theory and reality, BR Research inquires.
“For arguments sake, even if we take a conservative estimate
and say that the actual potential may well be one-eighth of the theoretical
potential, we are still talking about more than 20,000 MW,” Kashif replies.
“In the Rajasthan corridor, India, which is the backyard of
our Sindh corridor, their installed wind energy capacity is 18000 MW,” he adds.
Responding to a question on size of investment, Kashif agrees that per mega watt investment required for producing is higher in the case of wind energy.
However, he maintains that a comparison only in terms of investment is flawed; because in the case of wind there is no fuel cost. “In terms of tariff, many thermal tariffs based on fuel oil arehigher than the tariff for wind projects, whereas for wind the tariffs are 13-14 cents, which is fixed for next 20 years, unlike the thermal one, where the cost of fuel may increase the tariff any time in future during the project life” he said. Surely in case of hydro the tariff is far less and gas fired plants may be still cheaper than renewables at the moment but the requirement of renewables is a must from the point of view of Energy Mix of a country.
POLICY ENVIRONMENT
Kashif say that a number of wind energy projects totalling about 1000-1200 MW are expected to commence operations in the next few years.
However, he does expect much after that because of pending issues with the evacuation of power.
“For the projects that are underway, the NTDC has started
towards putting up the grid. But it appears that for the next wave to come in,
we have to gear up ourselves on that grid side,” he said. He added that the
NTDC had been delaying the signing of EPAs because there was no progress on the
loops needed to connect he projects with the main grid.
“If the government is really willing to push wind energy, it
can privatise the grid for the section that connects wind projects to the main
grid. There will be investors who will be ready to invest, as a separate
project,” he said. Explaining the nitty-gritty, Kashif says that the ball park cost of connecting the upcoming cluster of wind projects, for which the government is signing EPAs these days, to the main grid would be around $50-70 million. “With a debt/equity of 80:20, the equity requirement would be $14 million, which is an easy investment for those that already have stakes in wind power sector.”
While Kashif thinks the country’s renewable energy policy is “very good” with the “right incentives”, he suggests improvements in two areas.
“The policy does not stipulate the time during which the EPA
or IA must be signed, which means the government can delay the EPA or IA till
such time it wants. If we have to improve the policy, we have to spell out
realistic timelines for various processes,” he said.
DEMOCRATISATION OF
ENERGY The second aspect of improvement lies in what he calls the democratisation of energy. “The renewable energy policy talks about allowing households to produce solar energy and putting excess production on the grid. But it only talks about it in one paragraph.
“The government has simply ticked a check box. But is there
any detail to that? No. Are there any established rules to that? No. The
government has to come up with a detailed policy and regulatory framework to
incentivise individual consumer to come in as a small investor in the power
sector,” says Kashif.
He adds that Pakistan
has very good radiation levels all across the country which means that “we can
generate electricity at a distributed level”. Explaining his model, Kashif says that in order to reduce the requirement of the battery bank, the policy should be devised for a grid-tied system, where if there is excess energy, the producer can give it to the grid and the same producer uses the energy from the grid. And the metering can be done on a net basis.
But is it economical? “The good thing is that this does not entail a huge investment on any individuals.
A good system may
cost you roughly $1000 USD per kilowatt, which mean Rs300,000-400,000 for three
kilowatt. This seems expensive as upfront and it might not be enough for you to
have solar only. But it will take some of your load at lower cost of
production. The payback will be in 5-6 years, whereas the life of the panel is
20 years. And more importantly, it will make people part of the process,” he
replied.
Kashif added that the
government can incentivise the setting up costs by asking banks to give loans
to households to set up the solar panels, with the government picking up the
interest cost. “The move will trigger investments, which when pooled together,
will reduce the load on domestic consumption which is the biggest consumer,” he
said. He maintains that renewable is the only energy that can be produced efficiently at household level. “Millions of households and SME are currently producing thermal energy via generators, but at obnoxiously inefficient rates. It produces a unit at Rs40-50. Look at the foreign exchange which is being wasted due to this; had this money been pooled, we could have had three times the power produced,” he said.

No comments:
Post a Comment